Future Park Construction Progress

BLOCK A

Finishing works continue.

BLOCK B

Finishing works continue. Exterior sheathing works continue.

BLOCK C

Tunnel formwork installation will start on 16th typical floor.

BLOCK D

Tunnel formwork installation will start on 21st typical floor.

BLOCK C4 (CAR PARKING)

Columns&walls steelfixing and formworks continue on 2nd basement floor.

BLOCK E

Preparations for flats handing over continue.

BLOCK F

Preparations for flats handing over continue.

BLOCK G

Preparations for flats handing over continue.

BLOCK H (HOTEL)

Finishing works continue.

BLOCK I(RESIDENCE)

Finishing works continue. Exterior thermal sheathing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Finishing works continue.

BLOCK A

Finishing works continue.

BLOCK B

Finishing works continue. Exterior sheathing works continue.

BLOCK C

Tunnel formworks shall start.

BLOCK D

Tunnel formworks shall start.

BLOCK C2 (CAR PARKING)

Swimming pool formworks continue.

BLOCK C3 (CAR PARKING)

Ground floor slab steelfixing continues.

BLOCK C4 (CAR PARKING)

3rd basement floor slab steelfixing continues.

BLOCK E

Electrical, mechanical and finishing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Finishing works continue.

BLOCK I(RESIDENCE)

Finishing works continue. Exterior thermal sheathing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Finishing works continue.

BLOCK A

Finishing works continue.

BLOCK B

Finishing works continue. Façade platform setup continue.

BLOCK C

Columns&walls steelfixing started on 16th typical floor. Tunnel formwork installation will start.

BLOCK D

Tunnel formwork installation will start on 21st typical floor.

BLOCK C2 (CAR PARKING)

Slab steelfixing on ground floor continues.

BLOCK C3 (CAR PARKING)

SColumns&walls steelfixing and formworks started on ground floor continue.

BLOCK C4 (CAR PARKING)

Columns&walls steelfixing and formworks started on 3rd basement floor continue.

BLOCK E

Electrical, mechanical and finishing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Finishing works continue.

BLOCK I(RESIDENCE)

Finishing works continue. Exterior thermal sheathing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Finishing works continue in the shopping mall blocks.

BLOCK A

Finishing works continue.

BLOCK B

Finishing works continue. Façade working platform setup has started.

BLOCK C

Preparation of columns&walls steelfixing started on 15th typical floor.

BLOCK D

Slab concreting in the first stage and columns&walls steelfixing in the 2nd stage of 19th typical floor continue.

BLOCK C2 (CAR PARKING)

Slab concreting on 1st basement floor finished. Columns&walls steelfixing on ground floor shall start.

BLOCK C3 (CAR PARKING)

Slab formworks on 1st basement floor continue.

BLOCK C4 (CAR PARKING)

Columns&walls formworks shall start on 4th basement floor.

BLOCK E

Electrical, mechanical and finishing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Structural works completed. Finishing works continue.

BLOCK I(RESIDENCE)

Finishing works continue. Exterior thermal sheathing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Finishing works continue in the shopping mall blocks.

BLOCK A

Finishing works continue.

BLOCK B

Finishing works continue.

BLOCK C

Preparation of columns&walls steelfixing started on 15th typical floor.

BLOCK D

Tunnel formworks of the first stage and columns&walls steelfixing of the second stage on 17th typical floor.

BLOCK C2 (CAR PARKING)

Slab concreting on 2nd basement floor finished.

BLOCK C3 (CAR PARKING)

Slab steelfixing on 2nd basement floor continue. Slab concreting shall start.

BLOCK C4 (CAR PARKING)

Columns&walls steelfixing completed on 4th basement floor. Formworks shall start.

BLOCK E

Electrical, mechanical and finishing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Slab steelfixing continues on the roof floor boiler room. Finishing works started.

BLOCK I(RESIDENCE)

Structural works completed. Finishing works continue. Façade thermal sheathing works started.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, roof steel structure works have been finished. Finishing works continue in the shopping mall blocks.

BLOCK A

Conventional formworks and steelfixing for roof boiling room continue. Finishing works continue.

BLOCK B

Finishing works continue.

BLOCK C

Preparation of columns&walls steelfixing started on 15th typical floor.

BLOCK D

Slab concreting in the first stage on 14th typical and Preparation of columns&walls steelfixing in the 2nd stage continue.

BLOCK C2 (CAR PARKING)

Columns&walls steelfixing&formworks on 2nd basement floor continue.

BLOCK C3 (CAR PARKING)

Columns&walls steelfixing&formworks on 2nd basement floor continue.

BLOCK C4 (CAR PARKING)

Slab concreting completed on 5th basement floor.

BLOCK E

Electrical, mechanical and finishing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Slab steelfixing continues on the roof floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing completed on the roof floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, , Roof Steel Structure Works and Finishing works continue.

BLOCK A

Conventional formworks and steelfixing for roof boiler room continue. Finishing works continue.

BLOCK B

Structural works completed. Finishing works continue.

BLOCK C

Concreting continue at 1st stage of 14th typical floor. Preparation of columns&walls steelfixing started at 2nd stage of 14th typical floor.

BLOCK C2 (CAR PARKING)

Columns&walls concreted on 3rd basement floor. Slab formworks started.

BLOCK C3 (CAR PARKING)

Columns&walls steelfixing&formworks and concreting on 3rd basement floor continue.

BLOCK C4 (CAR PARKING)

Raft foundation steelfixing and concreting completed. Columns&walls steelfixing and formworks and concreting continue on 5th basement floor.

BLOCK E

Electrical, mechanical and finishing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Slab steelfixing continues on 28th typical floor.

BLOCK I(RESIDENCE)

Slab steelfixing continues on 28th typical floor. Finishing works continue. Façade working platform installation completed.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, roof steel structure works shall start; finishing works started.

BLOCK A

Conventional formworks and steelfixing for roof boiling room continue. Finishing works continue.

BLOCK B

Conventional formworks continue. Finishing works continue.

BLOCK B3 (CAR PARKING)

Structural works completed.

BLOCK C

Preparation of columns&walls steelfixing started on 11th typical floor. Tunnel formworks shall start. Finishing works continue.

BLOCK C2 (CAR PARKING)

Columns&walls steelfixing&formworks on 4th basement floor continue. Ramp slab concreting completed on 4th basement floor.

BLOCK C3 (CAR PARKING)

Columns&walls steelfixing&formworks on 4th basement floor continue.

BLOCK C4 (CAR PARKING)

Earthworks continue. Raft foundation steelfixing shall start.

BLOCK E

Electrical, mechanical and finishing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Slab steelfixing continues on 27th typical floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing completed on 28th typical floor, formworks to start. Finishing works continue. Façade working platform installation continued.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block F1, structural works completed.

BLOCK A

Tunnel formworks completed. Conventional formworks on roof boiling room and finishing works continue.

BLOCK B

Finishing works continue.

BLOCK B2 (CAR PARKING)

Structural works completed.

BLOCK B3 (CAR PARKING)

Slab steelfixing continue on ground floor; to be concreted.

BLOCK C

Finishing works continue.

BLOCK C2 (CAR PARKING)

Columns&walls concreting on 5th basement floor completed; slab formworks continue.

BLOCK C3 (CAR PARKING)

Raft foundation concreting completed. Concreting on 5th basement floor completed; slab formworks continue.

BLOCK E

Electrical, mechanical and finishing works continue. Dismounting of working paltforms completed on façades.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Columns&walls steelfixing shall start on 27th typical floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing completed on 27th typical floor, formworks to start. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block F1, slab formworks continue on 1st basement floor.

BLOCK A

2nd stage tunnel formworks on 29th typical floor continue. Conventional formworks and finishing works continue.

BLOCK B

Slab concreting completed on roof boiling room. Finishing works continue.

BLOCK B2 (CAR PARKING)

Slab concreting continues on ground floor.

BLOCK B3 (CAR PARKING)

Slab concreting completed on 2nd basement floor.

BLOCK C

Finishing works continue.

BLOCK C2 (CAR PARKING)

Concreting of raft foundation completed. Columns&walls steelfixing on 5th basement floor to start.

BLOCK C3 (CAR PARKING)

Raft foundation steelfixing started.

BLOCK C4 (CAR PARKING)

Electrical, mechanical and finishing works continue. Dismounting of working paltforms continues on façades.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works completed.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works completed on three façades and continue on the last façade.

BLOCK G

Electrical, mechanical and finishing works continue.

BLOCK H (HOTEL)

Slab steelfixing continues on 25th typical floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing & formworks completed on 26th typical floor 2nd stage, concreting to start. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block F1, slab concreting on 2nd basement floor.

BLOCK A

1st stage concreting & 2nd stage columns&walls steelfixing of tunnel formwork on 26th typical floor continue. Conventional formworks and finishing works continue.

BLOCK B

Conventional formworks continue on roof boiling room. Finishing works continue.

BLOCK B2 (CAR PARKING)

Slab formworks continue on ground floor.

BLOCK B3 (CAR PARKING)

Slab formworks continue on 2nd basement floor.

BLOCK C

Finishing works continue.

BLOCK C2 (CAR PARKING)

Steelfixing of raft foundation continues, concreting to be carried out.

BLOCK C3 (CAR PARKING)

Excavation works completed. Screed concrete below raft foundation completed.

BLOCK C4 (CAR PARKING)

Excavation works continue.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works completed, dismounting of working paltforms continues.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works completed on three façades and continue on the last façade.

BLOCK G

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works completed.

BLOCK H (HOTEL)

Slab formworks continue on 24th typical floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing started on 25th typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block F1, slab formworks continue on 2nd basement floor.

BLOCK A

2nd stage concreting of tunnel formworks on 23rd typical floor completed. 1st stage columns&walls steelfixing on 24th typical floor started. Conventional formworks continue.

BLOCK B

Conventional formworks continue on roof boiling room. Finishing works continue.

BLOCK B2 (CAR PARKING)

Columns&walls formworks continue on 1st basement floor.

BLOCK B3 (CAR PARKING)

Slab steelfixing continues on 3rd basement floor; concreting to start.

BLOCK C

Finishing works continue.

BLOCK C4 (CAR PARKING)

Excavation works continue.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK G

Electrical, mechanical, finishing and façade works continue.

BLOCK H (HOTEL)

Columns&walls steelfixing started on 24th typical floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing and formworks continued on 24th typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block F1, slab steelfixing continue on 3rd basement floor; concreting to start.

BLOCK A

Tunnel formworks on 22nd typical floor continue. Conventional formworks continue.

BLOCK B

BConventional formworks continue on roof boiling room. Finishing works continue.

BLOCK B2 (CAR PARKING)

Columns&walls formworks continue on 1st basement floor.

BLOCK B3 (CAR PARKING)

Slab formworks start on 4th basement floor.

BLOCK C

Finishing works continue.

BLOCK C2

Screed concrete completed.

BLOCK C4 (CAR PARKING)

Excavation works continue.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK G

Electrical, mechanical, finishing and façade works continue.

BLOCK H (HOTEL)

Slab steelfixing started on 23rd typical floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing and formworks continued on 23rd typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, 2nd stage, beams steelfixing continues on ground floor (last floor).

Block F1, slab formworks continue on 3rd basement floor.

BLOCK B

Concreting of 30th typical floor slab continue. Conventional formworks continue. Finishing works continue.

BLOCK B3 (CAR PARKING)

Slab formworks and steelfixing continue on 5th basement floor. Ramp slab concreting continue.

BLOCK C

Finishing works continue.

BLOCK C4 (CAR PARKING)

Excavation works started.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK G

Electrical, mechanical, finishing and façade works continue.

BLOCK H (HOTEL)

Slab formworks and steelfixing continue on 22nd typical floor.

BLOCK I(RESIDENCE)

Columns&walls steelfixing started on 22nd typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, 2nd stage, columns&walls steelfixing & formworks continue on ground floor.

Block F1, 1st stage slab concreting completed; 2nd stage slab formworks continue on 4th basement floor.

BLOCK B

Tunnel formwork shall start on 29th typical floor. Conventional formworks continue. Finishing works continue.

BLOCK B2

1st basement floor ramp slab steelfixing continues.

BLOCK B3 (CAR PARKING)

Columns&walls steelfixing continue on 5th basement floor.

BLOCK C

Finishing works started.

BLOCK C2 (CAR PARKING)

Raft foundation stage 2 concreting completed.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK G

Electrical, mechanical, finishing, façade works continue.

BLOCK H(HOTEL)

Slab formworks continue on 21st typical floor.

BLOCK I (RESIDENCE)

Columns&walls steelfixing started on 21st typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, 2nd stage, columns&walls steelfixing & formworks continue on 1st basement floor.

Block F1, slab formworks continue on 4th basement floor.

BLOCK B

Tunnel formwork shall start on 28th typical floor. Conventional formworks continue.

BLOCK B2

1st basement floor column formworks continued.

BLOCK B3 (CAR PARKING)

Concreting of raft foundation completed. Columns&walls steelfixing started on 5th basement floor.

BLOCK C2 (CAR PARKING)

Raft foundation stage 1 concreting completed. Raft foundation stage 2 steelfixing continues.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK G

Electrical, mechanical, finishing, façade works continue.

BLOCK H(HOTEL)

Columns&walls steelfixing works started on 21st typical floor.

BLOCK I (RESIDENCE)

Slab formworks shall start on 20th typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, 2nd stage, slab steelfixing continue on 2nd basement floor.

Block F1, slab formworks continue on 4th basement floor. Earthworks completed around the Block.

BLOCK A

Conventional formworks continue. Backfilling works around the Block completed.

BLOCK B

Tunnel formwork shall start on 27th typical floor. Conventional formworks continue.

BLOCK B2 (CAR PARKING)

1st basement floor column formworks started.

BLOCK C3 (CAR PARKING)

Earthworks completed.

BLOCK E

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works started.

BLOCK G

Electrical, mechanical, finishing, façade works continue.

BLOCK H(HOTEL)

Slab steelfixing works completed on 19th typical floor prior to slab concreting.

BLOCK I (RESIDENCE)

Columns&walls steelfixing works started on 19th typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING BLOCKS)

Block A2, 2nd stage, slab formworks continue on 2nd basement floor & columns&walls steelfixing works continue on 1st basement floor. Backfilling works completed around the Block.

Block F1, slab formworks continue on 4th basement floor. Earthworks continue around the Block.

Block F1, 2nd stage, raft foundation concreting completed & walls steelfixing and formworks continue. Earthworks continue around the Block.

BLOCK A

Conventional formworks continue. Backfilling works continue around the Block.

BLOCK B

Tunnel formwork continues on 24th typical floor. Conventional formworks continue.

BLOCK C2 (CAR PARKING)

Raft foundation concreting completed at Stage 1. Wall concreting completed on 5th basement floor.

BLOCK C3 (CAR PARKING)

Earthworks continue.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling completed in shared areas. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Exterior thermal sheathing works shall start.

BLOCK G

Electrical, mechanical, finishing, façade works continue and sample flat preparation works completed.

BLOCK H(HOTEL)

Slab steelfixing completed on 18th typical floor, slab concreting shall start.

BLOCK I (RESIDENCE)

Columns&walls steelfixing works started on 18th typical floor. Finishing works continue.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block A2, 2nd stage, columns&walls steelfixing and formworks continue on 2nd basement floor. Backfilling works continue around the Block.

Block F1, slab formworks continue on 4th basement floor. Earthworks continue around the Block.

BLOCK A

Conventional formworks continue. Backfilling works continue around the Block.

BLOCK B

Tunnel formwork continues on 22nd typical floor. Conventional formworks continue.

BLOCK B2 (CAR PARKING)

2nd basement floor slab concreting completed.

BLOCK B3 (CAR PARKING)

Earthworks completed. Raft foundation steelfixing works shall start.

BLOCK C2 (CAR PARKING)

Earthworks completed. Lean concreting completed at stage 1.

BLOCK C3 (CAR PARKING)

Earthworks continue.

BLOCK D

New sample flat works completed on 1st typical floor. Conventional formworks continue.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue.

BLOCK G

Electrical, mechanical, finishing, façade works and sample flat preparation works continue.

BLOCK H(HOTEL)

Columns and walls concreting completed on 17th typical floor, slab formworks started.

BLOCK I (RESIDENCE)

Slab steelfixing works continue on 16th typical floor. Finishing works have started.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block A2, 2nd stage, columns&walls steelfixing and formworks continue on 3rd basement floor. Backfilling works continue around the Block

Block E5, structural works completed.

Block F1, raft foundation concreting completed; 5th basement floor columns steelfixing shall start.

BLOCK A

Conventional formworks continue. Backfilling works continue around the Block.

BLOCK B

Tunnel formwork continues on 21st typical floor. Conventional formworks continue.

BLOCK B2 (CAR PARKING)

2nd basement floor columns & walls formworks continue.

BLOCK B3 (CAR PARKING)

Earthworks started. Lean concrete laying tomorrow, and then raft foundation steelfixing works.

BLOCK D

New sample flat works continued on 1st typical floor. Conventional formworks continue.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Structural works completed.

BLOCK G

Electrical, mechanical, finishing, façade works and sample flat preparation works continue.

BLOCK H(HOTEL)

Columns and walls steelfixing works continue on 16th typical floor.

BLOCK I (RESIDENCE)

Slab formworks continue on 15th typical floor.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block A2, 1st stage works completed. 2nd stage works continue on 4th basement floor slab formworks steelfixing. Backfilling works continue around the Block

Block F1, lean concrete completed. Raft foundation steelfixing shall start.

Block E5, 1st basement floor slab steelfixing continued, concreting shall start.

BLOCK A

Conventional formworks continue. Backfilling works continue around the Block.

BLOCK B

Tunnel formwork continues on 16th typical floor. Conventional formworks continue.

BLOCK B2

4th basement floor columns & walls formworks continue.

BLOCK D

New sample flat works continued on 1st typical floor. Conventional formworks continue.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Roof perimeter wall was cast, boiler room reinforcement works shall start.

BLOCK G

Electrical, mechanical, finishing, façade works and sample flat preparation works continue.

BLOCK H(HOTEL)

Slab steelfixing and shuttering works continue on 13th typical floor.

BLOCK I (RESIDENCE)

Columns&walls steelfixing works shall start on 14th typical floor.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block A2, 1st basement floor, 1st stage slab shuttering continues and 2nd stage 5th basement floor columns&walls steelfixing and shuttering works continue.

Block F1, second row of anchoring of surrounding shoring piles continues. Earthworks continue for foundation.

Block E5, 3rd basement floor columns&walls steelfixing started.

BLOCK A

Tunnel formwork continue on 21th typical floor. Conventional formworks continue. Backfilling works continue around the Block.

BLOCK B

Tunnel formwork continues on 15th typical floor. Conventional formworks continue.

BLOCK B2

Raft foundation steelfixing works started.

BLOCK D

New sample flat works continued on 1st typical floor. Conventional formworks continue.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Concreting of walls and columns, preparation for slab formwork on 9th typical floor.

BLOCK G

Electrical, mechanical, finishing, façade works and sample flat preparation works continue.

BLOCK H(HOTEL)

Slab steelfixing and shuttering works continue on 10th typical floor.

BLOCK I (RESIDENCE)

Columns&walls steelfixing works continue on 15th typical floor.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block A2, 2nd basement floor, 1st stage slab shuttering continues and 2nd stage raft foundation steelfixing works started.

Block F1, anchoring of surrounding shoring piles completed. Earthworks continue for foundation.

Block F2, structural works completed.

Block E4, structural works completed.

Block E5, raft foundation concreting completed; 5th basement floor columns&walls works shall start.

Block E6, structural works completed.

BLOCK A

Tunnel formwork continue on 15th typical floor. Conventional formworks continue.

BLOCK B

Tunnel formwork completed on 14th typical floor. Conventional formworks continue.

BLOCK D

New sample flat works started on 1st typical floor. Conventional formworks continue.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Exterior thermal sheathing works continue.

BLOCK F

Electrical, mechanical and finishing works continue. Steelfixing of walls and columns started on 8th typical floor.

BLOCK G

Electrical, mechanical, finishing, façade works and sample flat preparation works continue.

BLOCK H(HOTEL)

Columns&walls steelfixing and shuttering works continue on 7th typical floor.

BLOCK I (RESIDENCE)

Slab steelfixing works continue on 12th typical floor.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block A2, 3rd basement floor slab shuttering works started.

Block F1, anchoring of surrounding shoring piles continues. Earthworks continue for foundation.

Block F2, 3rd. basement floor columns&walls steelfixing continue.

Block E4, 3rd. basement floor slab steelfixing continue.

Block E6, 1st. basement floor slab steelfixing continue.

BLOCK A

Tunnel formwork completed on 13th typical floor. Conventional formworks continue. Masonry works continue on 12th typical floor.

BLOCK B

Tunnel formwork continues on 13th typical floor. Conventional formworks continue.

BLOCK D

Sample flat finishing works completed on 1st typical floor. Earthworks continue for the neighbor car parking building.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Exterior thermal sheathing works started

BLOCK F

Electrical, mechanical and finishing works started.

BLOCK G

Electrical, mechanical, finishing, façade works and sample flat preparation works continue. PVC joinery window fixing completed on three façades.

BLOCK H(HOTEL)

Columns&walls reinforcement works shall start on 5th typical floor.

BLOCK I (RESIDENCE)

Columns&walls reinforcement works continued on 11th typical floor.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block F3 structural works completed.

Block F2, 5th. basement floor slab shall be concreted.

Block F1 capping beam concreting continues.

4th. basement floor columns&walls concreting works continue.

Block E4 raft foundation concreting completed. 5th. basement floor columns&walls reinforcement works continue.

Block E6 raft foundation concreting completed. 2nd. basement floor columns&walls reinforcement works continue.

BLOCK A

Tunnel formwork continues on 12th typical floor. Conventional formworks continue.

BLOCK B

Vicinity backfilling works completed. Masonry works completed on 9th typical floor.

BLOCK D

Sample flat finishing works continue on 1st typical floor.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Exterior thermal sheathing works shall start.

BLOCK F

Electrical, mechanical and finishing works started.

BLOCK G

Electrical, mechanical, finishing works continue. Exterior façade paintwork continues. PVC joinery window fixing continues on two façades.

BLOCK H(HOTEL)

Slab concreting on 1st typical floor.

BLOCK I (RESIDENCE)

Columns and walls shuttering and reinforcement works continued on 9th typical floor.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block F5 concreting works completed.

Block F3 2nd basement floor slab shuttering started.

Block F2 raft foundation completed, Columns and walls reinforcement works continued on 5th basement floor.

Block F1 shoring piling completed, capping beam and anchoring shall start.

Block A2 raft foundation reinforcement works continue.

BLOCK A

Conventional formworks continue. Tunnel formworks shall resume.

CAR PARKING BETWEEN BLOCKS A & B

Structural concreting works completed.

BLOCK B

Vicinity backfilling works continue. 8. typical floor masonry works continued.

BLOCK C

Vicinity backfilling works completed.

BLOCK D

Block vicinity backfilling and capping beam works completed. 1. Typical floor sample flat finishing works continue.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Working platform mounting completed at one of the exterior façades, exterior thermal sheathing works shall start there.

BLOCK F

7. typical floor masonry works completed. Electrical and mechanical works shall start.

BLOCK G

Electrical, mechanical, finishing works continue. Exterior thermal sheathing and PVC joinery works completed at three façades. Exterior painting continues.

BLOCK H(HOTEL)

First basement floor columns and walls shuttering works continued.

BLOCK I (RESIDENCE)

6. typical floor slab shuttering and reinforcement works continued.

FUTURE PARK MALL (BLOCK F SHOPPING)

Block F5 2nd basement floor columns and walls steelfixing, shuttering and concreting continued. Block F3 5th basement floor slab steelfixing and shuttering continued. Block F2 earthworks completed, raft foundation works shall start. Block F1 shoring piling continued. Block A2 earthworks and capping beam completed, raft foundation works shall start.

BLOCK A

10. typical floor concreting completed, conventional formworks continue.

CAR PARKING BETWEEN BLOCKS A & B

2. basement floor slab reinforcement works continue.

BLOCK B

Vicinity backfilling works continue. Capping beam works completed in front of this block. 3. typical floor masonry works continued.

BLOCK C

Vicinity backfilling works continue.

BLOCK D

9. typical floor masonry works completed. Block vicinity backfilling works continue. Shoring piling works completed & capping beam starts near this block.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues in shared areas. Platform mounting started at exterior façades.

BLOCK F

5. typical floor masonry works continued.

BLOCK G

Electrical, mechanical, finishing and exterior thermal sheathing works continue. PVC frames fixing started.

BLOCK H(HOTEL)

Ground floor slab shuttering works started.

BLOCK I (RESIDENCE)

3. typical floor slab concreting continue.

FUTURE PARK MALL (BLOCK F SHOPPING)

F5 Block 4. basement floor slab steelfixing continues. F3 Block raft foundation concreting completed, 5. basement floor concrete walls reinforcement works started.

BLOCK A

6. typical floor tunnel formworks continue.

CAR PARKING BETWEEN BLOCKS A & B

Raft foundation concreting completed. 3. Basement floor reinforcement works and formworks continue at columns and walls.

BLOCK B

Vicinity backfilling works continue. Capping beam reinforcement works continue in front of this block.

BLOCK C

Vicinity backfilling works continue.

BLOCK D

Masonry works continued. Block vicinity backfilling works continue. Capping beam reinforcement works continue in front of this block.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues inside the flats.

BLOCK F

7. typical floor slab concreting completed. Masonry works started.

BLOCK G

Electrical, mechanical, finishing and exterior thermal sheathing works continue.

BLOCK H(HOTEL)

4. Basement floor steelfixing and shuttering works continue at columns and walls.

BLOCK I (RESIDENCE)

2. typical floor slab formworks started.

FUTURE PARK SHOPPING AREA (BLOCKS F)

5. Basement floor steelfixing and shuttering works continue at columns and walls.

BLOCK A

1. basement floor tunnel formworks continue.

CAR PARKING BETWEEN BLOCKS A & B

Screed concreting completed. Raft foundation reinforcement works shall start.

BLOCK B

Concreting of 10. typical floor completed. Conventional formworks continue.

CAR PARKING BETWEEN BLOCKS B & C

Rough construction works completed.

BLOCK C

Block C vicinity backfilling works continue.

BLOCK D

Conventional formworks completed. Masonry works started. Block vicinity backfilling works continue. Rough construction works completed for power transformer structure beside Block D.

BLOCK E

Electrical, mechanical and finishing works continue. Low and high voltage cabling continues inside the flats.

BLOCK F

7. typical floor shuttering and steelfixing continues.

BLOCK G

Electrical, mechanical, finishing and exterior thermal sheathing works continue.

BLOCK H(HOTEL)

Raft foundation concreting completed. 5. Basement floor steelfixing and shuttering works continue.

BLOCK I (RESIDENCE)

1. typical floor steelfixing and shuttering works started.

FUTURE PARK MALL

Raft foundation concreting completed.

BLOCK A

Steelfixing works for columns of 2. Basement floor of Block A completed.

BLOCK B

Steelfixing works for columns of 10. typical floor of Block B started.

BLOCK C

Block C vicinity backfilling works continue.

BLOCK D

Block D conventional formworks continue. Block D vicinity backfilling works continue. Slab shuttering works for power transformer structure beside Block D started.

BLOCK E

Electrical, mechanical and finishing work productions are ongoing. Low and high voltage cabling continues inside the flats.

BLOCK F

Block F 5. typical floor slab shuttering and steelfixing completed.

BLOCK G

Electrical, mechanical and finishing work productions are ongoing. Exterior thermal sheathing works continue.

BLOCK H(HOTEL)

Bored piling foundation works completed. Screed concreting continues. Raft foundation steelfixing works shall start.

BLOCK I (RESIDENCE)

First basement floor slab shuttering continues.

FUTURE PARK SHOPPING AREA (BLOCKS F)

Block F shopping area screed concreting continues.

CAR PARKING

Car parking between Blocks B & C; 2. Basement floor slab shuttering continues.

BLOCK A

Raft foundation concreting completed. Third basement floor tunnel formworks started.

BLOCK B

Fifth typical floor tunnel formworks continue.

BLOCK C

Conventional works continue. Backfilling around the block continues.

BLOCK D

Conventional works continue. Backfilling around the block continues.

BLOCK E

Electrical and Mechanical works continue. Low and high current cabling works continue in the flats. Finishing works continue. Skylight is completed. PVC windows delivered to site.

BLOCK F

Third typical floor slab formworks continue.

BLOCK G

Electrical and Mechanical works continue. Finishing works continue. Skylight is completed. Exterior thermal sheathing works started.

BLOCK H(HOTEL)

Excavation works completed. Bored piling works for foundation started.

BLOCK I (RESIDENCE)

Third basement floor columns reinforcement works continue.

FUTURE PARK SHOPPING AREA (BLOCKS F)

Old sales office area excavation works continue.

BLOCK A

Block A bored piling works completed. Blinding concrete completed.

BLOCK B

Block B ground floor tunnel formworks ongoing.

BLOCK C

Block C surrounding backfilling is ongoing.

BLOCK D

Block D conventional concreting works ongoing. Block D surrounding backfilling is ongoing.

BLOCK E

Electrical and mechanicalworks ongoing. Low and high current cabling in the flats ongoing. Finishing Works started. Roof skylight works ongoing.

BLOCK F

First floor slab concreting started.

BLOCK G

Electrical and mechanicalworks ongoing. Finishing Works ongoing. Roof skylight frames installation will start.

BLOCK I

Fourth floor columns steelfixing Works ongoing.

FUTURE PARK SHOPPING AREA

Excavation Works ongoing.

BLOCK A

Bored piling for raft foundation continues.

BLOCK B

Tunnel formwork for third basement floor continues.

BLOCK C

Backfilling around the Block continues. Concrete works for car parking building between Blocks C & D completed.

BLOCK D

Conventional formwork continues. Backfilling around the Block continues.

BLOCK E

Electrical & Mechanical works continue. Low and high current cabling in flats continues. Steel structure works for roof skylight continue.

BLOCK F

Ground floor formworks continue.

BLOCK G

Electrical, Mechanical & Finishing works continue.

BLOCK I

Raft foundation concreting completed. 5. Basement floor columns formworks continue.

FUTURE PARK SHOPPING AREA

Excavation of old sales center area continues.

BLOCKS A – B

Earthworks completed and bored-piled deep foundation works started at Block A. Earthworks for water tank installation completed between Blocks A & B.

BLOCK C

Tunnel formwork and concreting of 10. typical floor at Block C completed. Backfilling around Block C continues. Steelfixing works for columns of 1. Basement floor of Car Parking Building between Blocks C & D continues.

BLOCK D

Tunnel formwork and concreting of 10. typical floor at Block D completed. Backfilling around Block D continues. Conventional shuttering works continues at Block D.

BLOCK E

Low and high voltage cabling continues inside the flats.

BLOCK F

1. Basement floor columns concreting continues and slab formwork preparation started.

BLOCK G

Electrical, mechanical and finishing work productions are ongoing.

BLOCK I

Bored piling deep foundation works completed. Raft foundation steelfixing works continues.

FUTURE PARK SHOPPING AREA

Dismantling of the former sales office structure continues. Earthworks shall start.

BLOCKS A – B

Earthworks ongoing in the vicinity of Blocks A – B.

BLOCK C

Backfilling started around Block C. Car Parking (between Blocks C&D), basement floor #2, steelfixing works for columns completed.

BLOCK D

Tunnel Formwork And Concreting ongoing at Floor #9. Backfilling around the Block ongoing.

BLOCK E

Low and high voltage cabling ongoing inside the flats. Brick Walling activity completed.

BLOCK F

Basement Floor #3, concreting of columns ongoing.

BLOCK G

Electrical, mechanical and finishing work productions are ongoing.

BLOCK I

Bored piling deep foundation works ongoing.

FUTURE PARK SHOPPING AREA

As part of Shopping Area construction preparation, the shifting of selling office location from Block E area to Block G area (Block F4) was completed. The preparation of Sales Office was also completed and became operational. Excavation and shoring activities proceed with speed at Blocks F shopping area.

BLOCKS A – B

Shoring between Blocks A & B completed. Blinding concrete cast at Car parking between Blocks A & B

BLOCK C

Conventional concreting activities ongoing at typical floors. Car Parking Basement Floor #3 Formwork Preparation Works started.

BLOCK D

Tunnel Formwork And Concreting ongoing at Floor #7. Backfilling around the Block ongoing.

BLOCK E

Low and high voltage cabling ongoing inside the flats. Walling activity is ongoing.

BLOCK F

Block F Basement Floor #5 Formwork preparation completed.

BLOCK G

Electrical, mechanical and finishing work productions are ongoing.

FUTURE PARK SHOPPING AREA

As part of Shopping Area construction preparation, the shifting of selling office location from Block E area to Block G area (Block F4) is almost completed, with Management and Engineering Offices already completed and operational upstairs. The preparation of Sales Office is about to finish. Excavation and shoring activities proceed with speed at Blocks F area.

BLOCKS A – B

Installation of capping beam at North-Northeast of Block A completed. Excavation works started at Block A. Shoring piling between Blocks A & B is ongoing.

BLOCK C

Conventional concrete works at typical floors are ongoing. Concreting of carparking foundation between Blocks C & D completed. Reinforcement fixing for columns and beams is ongoing.

BLOCK D

Tunnel formwork and concreting is ongoing at 6. Typical floor. Backfilling is ongoing around the Block.

BLOCK E

Low and high voltage cabling ongoing inside the flats.Walling activity is ongoing at 20. Typical floor.

BLOCK F

Concreting completed at raft foundation. Reinforcement fixing for columns and beams is ongoing.

BLOCK G

Electrical, mechanical and finishing work productions are ongoing.

FUTURE PARK SHOPPİNG AREA (BLOCKS F)

As part of Shopping Area construction preparation, the shifting of selling office location from Block E area to Block G area (Block F4) is almost completed, with Management and Engineering Offices already completed and operational upstairs. Excavation and shoring activities proceed with speed at Blocks F area.